Project Project Information Estimated Project Cost Actual Project Cost Anticipated Start Date Anticipated Completion Date Project Status
Accordion Partitions, Curtains, Sound Systems Accordion Partitions, Curtains, Sound Systems Project Information $2,800,000 $2,109,500 Spring 2019 Fall 2020 Completed
ADA Restrooms Phase 1 ADA Restrooms Project Information $1,335,600 $523,709 Spring 2017 Summer 2018 Completed
ADA Restrooms Phase 2 ADA Restrooms Project Information $1,928,000 $1,928,000 Fall 2019 Summer 2020 Completed
Center for Advanced Careers CFAC Project Information $76,600,000 $63,791,358 Spring 2016 Summer 2018 Completed
Crump Stadium ADA Seating Crump ADA Seating Project Information $602,000 $676,000 Spring 2019 Summer 2020 Completed
Elsik High School Softball Competition Field Elsik Softball Competition Field Project Information
$334,000 $676,000 Fall 2020 Fall 2020 Completed
Entry Canopies Entry Canopies Project Information
$4,200,000 $4,465,000 Spring 2019 Summer 2020 Completed
Facility Assessment $69,831,400 $41,495,438 Spring 2016 Summer 2021 In Progress
Fieldhouse Weight Rooms Weight Rooms Project Information $500,000 $1,403,766 Summer 2018 Spring 2019 Completed
Kerr High School Fine Arts Addition Kerr Fine Arts Addition Project Information $14,200,000 $14,200,000 Spring 2016 Spring 2017 Completed
Middle School Gymnasium Additions Gym Additions Project Information $23,000,000 $22,951,024 Spring 2016 Spring 2017 Completed
Multi-Purpose Center (Alief Center for Talent Development) CTD Project Information $23,840,000 $19,058,513 Fall 2018 Fall 2020 Completed
Olle Middle School Ensemble Room Olle Ensemble Room Project Information $306,000 $306,000 (Bundled Together with Middle School Gyms) Spring 2016 Spring 2017 Completed
Outley Elementary School Addition Outley Addition Project Information $6,040,000 $5,928,963 Spring 2016 Spring 2017 Completed
Phase 3 District Wide Security Enhancements $2,000,000 $1,102,000 Spring 2018 Summer 2020 Completed
Pre-Kindergarten Facilities Pre-Kindergarten Facilities Project Information $85,000,000 $55,207,360 Spring 2020 Spring 2022 In Progress
Reception Areas Reception Areas Project Information $843,000 $843,000 (Bundled Together with Entry Canopy Project) Spring 2019 Summer 2020 Completed
Restrooms Upgrades Restrooms Upgrades Project Information $11,075,000 $5,107,618 Spring 2019 Summer 2021 In Progress
Safety Vestibules Safety Vestibules Project Information $10,530,000 $9,166,450 Spring 2017 Summer 2018 Completed
School Buses School Buses Project Information $9,000,000 $9,000,000 Spring 2016 Spring 2021 Completed
Youens Elementary School Library Expansion Youens Library Expansion Project Information $963,000 $849,000 Spring 2019 Summer 2020 Completed